10/27/2008: "Priorities"
Perhaps you are troubled by the recent staff layoffs and park closings. These budget cuts are the result of years of excess spending, misplaced priorities, and a lack of serious concern for maintaining an adequate reserve fund. This past period of indulgence has come to an abrupt end.
The summary of accounts below is an eye-opening look at how money was spent on a transfer station project that has little, if any, public support. The spending was authorized by a number of contracts with details described below.
Some of the work was performed in an attempt to create enthusiasm for a plan to relocate the dump. The plan was then taken to the point where it stands today; a final Environmental Impact Statement (EIS) is due before the end of the year, and a decision to move it or not, will be made by early next year. The project has still not generated much public support and appears to be doomed under a tight budget. Here is some background.
In June 2008, I requested information about the total cost of the DEIS for the transfer station project. Here is the response I got via email from Stan Mathews, 7/9/08:
The budget for the EIS for the Transfer station is scattered among several sections of the budget, but according to Jon Shannon, the total is approximately $150,000. If you need more detailed information, we'll have to have you curl up with the budget book. (Let me know.)
While researching the EIS documents, I found references to several reports generated by engineering contractors and consultants. I decided to request all of the contracts for EIS work. Mr. Matthews promptly directed Public Works to provide contract documentation of current costs for producing the Draft EIS and Final EIS for the San Juan “Transfer Station Relocation Project”.
Over the course of several hours I went through the 15 contracts and took the notes below. I have made condensed general comments about the scope of work for each contract. I tried to be precise and accurate in these abbreviated notes. The Council or the Administrator authorized the contracts. If you get to the bottom line it is obvious that the EIS cost a great deal more than Mr. Shannon stated and it is still adding up.
The following is a list of contract summaries between San Juan County Public Works and several different engineering and consulting groups. In my opinion this is an example of excess spending on a misplaced priority. After reading this you may agree.
Contract information for Transfer Station relocation project 2006-2008.
Contract # Date Contractor Amount of Contract
08SW.008 9/9/08 Allen Emerson....................$960.00
Scope of work summary:
Organize public Comments
08SW.001 2/25/08 Zender-Thruston................$25,000.00
Scope of work summary:
SJC hired attorney Robert Carmichael to represent
SJC and to assist PA’s office with work related to
Transfer station.
08SW.003 8/28/07 Picketts Engineering..........$33,000.00
Scope of work summary:
Revise conceptual layouts for DEIS including
Storm water, wetlands, etc. Excerpts:
6. “A planning level probable cost of construction
estimate will be prepared for each of the 5 layouts.”
8. “A memorandum summarizing planning level
cost estimates will be prepared.”
07SW.08 8/28/07 Picketts Engineering............$14, 000.00*
Scope of work summary:
*Same as above except $14, 000.00 is broken out
separately. This amount may be included in above cost.
06SW.11 8/7/06 Picketts Engineering................$9,950.00
Scope of work summary:
Prepare 4 conceptual layouts for August SWAC
Meeting. Compare existing vs new layout in generic form.
06SW.06 5/22/06 Picketts Engineering............$12,500.00
Scope of work summary:
Provide input to Norton-Arnold and Gary Harshman
(project managers). “obtain the County’s research
already conducted regarding curbside service on SJ.”
08SW.004 5/21/08 AMEC Earth & Enviro..........$139,801.01
Scope of work summary:
DEIS to be done according to scoping document.
Required to determine planning level costs including:
Acquisition, site development, construction, expansion,
operational, and maintenance costs. (I was told here will be additional
work and cost to this contract. I have not received details yet).
“As you know, there will be a final supplemental amendment to the AMEC contract 08SW004. I plan on getting you the cost and scope documentation this week to begin processing the supplemental.” 9/16/08 email from Steve Alexander
07SW.06 5/8/07 AMEC.....................................$81,543.40
Scope of work summary:
Scoping process development. Includes comparing
alternatives and description of relevant land use implications
of each alternative with Comp Plan, zoning, and ordinance
and identify all permitting issues.
07SW.03A 3/26/07 Environments........................$25,000.00
Scope of work summary:
Consulting services performed by Gary Harshman.
This is another company run/owned by Mr. Harshman who
Also signed contracts as president for AMEC. Work includes
Managing activities of team including Picketts, Donovan-Kehrer,
Norton-Arnold (Todd Peterson & Chris Hoffman). Develop
strategy for SEPA review, attend SWAC meetings.
06SW.07 5/22/06 Environments...........................$25,000.00
Scope of work summary:
Same scope as above different time period.
06SW.05A 5/11/06 Donovan-Kehrer & Assoc..........$7,500.00
Scope of work summary:
Professional project planning services.
07SW.07A 9/21/07 Norton-Arnold........................$23,011.56
Scope of work summary:
Services of Todd Peterson. Prepare and record summary
of public comments from scoping meeting.
Develop brochures for mailing.
07SW.07 5/24/07 Norton-Arnold..........................$19,017.00
Scope of work summary:
Services of Todd Peterson. Prepare public involvement
Plan for SEPA scoping process. Create mailer, update
Web site, newspaper advertising, etc.
07SW.01A 3/8/07 Norton-Arnold.........................$37,090.00
Scope of work summary:
Services of Todd Peterson. Develop public involvement
Program. Facilitate 6 SWAC meetings ($15,800.00 was
the amount paid for this as a line item for this or
$2,634.00 per meeting), hold “open house” meeting,
write news releases, interview stakeholders (12).
06SW.08 6/8/06 Norton-Arnold..........................$37,090.00*
Scope of work summary:
Same scope as above appears to be supplemental
To above contract but the date covered is different.
According to the note above this contract covered
Work that was preliminary to the DEIS. * One note
of explanation by Steve Alexander follows:
“Please note that the work scope for several of the oldest contracts covers non-DEIS work as well as DEIS work. In particular, only a small portion of the work scope in contract agreement 06SW08 was DEIS work.”
08CD.015 6/03/08 Herrera Enviromental..............$27,679.52
Scope of work summary:
Assist the County in reviewing the DEIS and the
final EIS and consult with CD&P then form written
comments.
Total cost of contracts........................................$518,142,.48
The contract for the final EIS is not included in the above costs. That contract is “still being worked up” as of 10/16/08.
So far the transfer station relocation project has cost taxpayers dearly. It is not clear that the project has public support or that we can even afford to build it. When we spend money like this and turn around and layoff county workers and close parks I think our priorities are wrong. How about you?